Highway inspection technology service

Chengdu Gaopan Road and lower Dongdajie section of Dongdajie are located in the prosperous section of Chengdu with large traffic volume. There are more heavy vehicles at night, and the roads are seriously damaged, and they are repaired many times. However, no comprehensive improvement project has been carried out, and the road safety problem has not been fundamentally solved. In particular, after the rainy season, the internal diseases should be examined in detail. Chengdu Guimu Robot Co., Ltd. is commissioned by the Chengdu Road and Bridge Management Institute to inspect the road diseases of Gaopan Road and lower Dongdajie section of Dongdajie.

Inspection area

This inspection is divided into two areas, namely Gaopan Road and lower Dongdajie section of Dongdajie, the inspection area is 500m2 and 1300m2 respectively,
and the duration of the two tasks is 30 minutes and 50 minutes respectively.

Gaopan Road

lower Dongdajie section of Dongdajie

Gaopan Road Detection area (in red box)

lower Dongdajie section of Dongdajie Detection area (in red box)

At the scene of the homework

At the scene of the homework

Test results

A total of 5 structural diseases were found in Gaopan Road, including 1 loose place and 4 empty places.

Test results

lower Dongdajie section of Dongdajie, there were 5 structural diseases, 4 loose ones and 1 local uneven settlement.

Highway inspection technology service

Highway inspection technology service

Chengdu Gaopan Road and lower Dongdajie section of Dongdajie are located in the prosperous section of Chengdu with large traffic volume. There are more heavy vehicles at night, and the roads are seriously damaged, and they are repaired many times. However, no comprehensive improvement project has been carried out, and the road safety problem has not been fundamentally solved. In particular, after the rainy season, the internal diseases should be examined in detail. Chengdu Guimu Robot Co., Ltd. is commissioned by the Chengdu Road and Bridge Management Institute to inspect the road diseases of Gaopan Road and lower Dongdajie section of Dongdajie.

Inspection area

This inspection is divided into two areas, namely Gaopan Road and lower Dongdajie section of Dongdajie, the inspection area is 500m2 and 1300m2 respectively, and the duration of the two tasks is 30 minutes and 50 minutes respectively.

Gaopan Road

Gaopan Road Detection area (in red box)

At the scene of the homework

Test results

A total of 5 structural diseases were found in Gaopan Road, including 1 loose place and 4 empty places.

lower Dongdajie section of Dongdajie

lower Dongdajie section of Dongdajie Detection area (in red box)

At the scene of the homework

Test results

lower Dongdajie section of Dongdajie, there were 5 structural diseases, 4 loose ones and 1 local uneven settlement.